Forum

A contract on const...
 
Notifications
Clear all

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs. 200 for the first day, Rs. 250 for the second day, Rs. 300 for the third day, etc., the penalty for each succeeding day being Rs. 50 more...

1 Posts
2 Users
0 Likes
268 Views
0
Topic starter

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs. 200 for the first day, Rs. 250 for the second day, Rs. 300 for the third day, etc., the penalty for each succeeding day being Rs. 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days.

1 Answer
0

First term as 200 and common difference as 50.

a = 200 and d = 50

Penalty that has to be paid if contractor has delayed the work by 30 days = S30

Sn = n/2[2a+(n -1)d]

Therefore,

S30= 30/2[2(200)+(30 – 1)50]

= 15[400+1450]

= 15(1850)

= 27750

Therefore, the contractor has to pay Rs 27750 as penalty.

Share:

How Can We Help?